In Abrud, Alba Iulia, we are executing the rehabilitation of main ovoid collector 750/500 mm. For rehabilitation works we use MazurLiner UV, fibre glass liner cured with UV rays. These are the first installation works of total length of 3,6 km of the collector. Part of it will be renovated with GRP modules in technology of the relining. Works are planned to be finished until the end of 2021.
The preparatory works have been started in the beginning of the first wave COVID-19, in the most uncertain period for our business and the economy in general. Despite of restrictions we managed to organize the works and until now we executed 1,2 km of lining with CIPP and 180 m of GRP modules relining.